2017-2022 Bond Program: South Presa Street (Southeast Military Drive to Southcross Boulevard)
2017-2022 Bond Program: South Presa Street (Southeast Military Drive to Southcross Boulevard)
The Bond Project will construct corridor improvements fom Military to Southcross. This includes pedestrian amenities and enhancements as appropriate and within available funding.
Phase: Complete
Project Contact: Joe Garcia - (210) 207-0097
Estimated Construction Timeline: Summer 2022 - Spring 2024
Estimated Timeline Construction Seasons are identified as: Winter (January, February, March), Spring (April, May, June), Summer (July, August, September), and Fall (October, November, December.)
Project Budget: | |
2012 General Obligation Bond (Street) | $8,675,400.46 |
| |
CPS Energy | $2,012,771.18 |
Presa Road Streets | $8,712,000.00 |
San Antonio Water System | $2,805,052.22 |
Total | $22,190,618.11 |
NOTE TO BUSINESS OWNERS:
If your business is currently or expected to experience construction in your area please visit the City of San Antonio's Construction Toolkit. This guide helps business owners understand and prepare for City-initiated construction projects.
Business Outreach Specialist: Monica Cantu, 210-207-3935
Learn more about City projects in your neighborhood and across San Antonio. The City of San Antonio’s digital dashboards encompass a wide range of projects, including streets, drainage, parks, and facilities.