2022-2027 Bond Project: Vance Jackson Road (Huebner Road to Wurzbach Road)
2022-2027 Bond Project: Vance Jackson Road (Huebner Road to Wurzbach Road)
The Bond Project will construct roadway improvements to include sidewalks, curbs, driveway approaches, and traffic improvements as applicable and within available funding.
Project Type: Streets, Bridges, & Sidewalks
Phase: Design
Project Contact: LaShondra Gladney - (210) 207-0620
Estimated Construction Timeline: Summer 2026 - Summer 2028
Estimated Timeline Construction Seasons are identified as: Winter (January, February, March), Spring (April, May, June), Summer (July, August, September), and Fall (October, November, December).
Project Budget: | |
2022 General Obligation Bond (Streets) | $ 16,000,000.00 |
CPS Energy | $ 131,288.13 |
San Antonio Water System | $ 270,400.20 |
Total | $ 16,401,688.33 |
NOTE TO BUSINESS OWNERS:
If your business is currently or expected to experience construction in your area please visit the City of San Antonio's Construction Toolkit. This guide helps business owners understand and prepare for City-initiated construction projects.
Learn more about City projects in your neighborhood and across San Antonio. The City of San Antonio’s digital dashboards encompass a wide range of projects, including streets, drainage, parks, and facilities.
Project Scope:
- Widen existing roadway by adding a consistent two-way center turn lane while preserving the character of the corridor.
- Construct improved sidewalks and a shared-use-path (SUP).
- Install underground drainage to low-water-crossing project.