2022-2027 Bond Project: District 2 F-Streets Reconstruction
2022-2027 Bond Project: District 2 F-Streets Reconstruction
The Bond Project will construct roadway improvements to include sidewalks, curbs, driveway approaches, and other improvements as applicable and within available funding.
While about 43 percent - or about 1,804 miles - of these streets make a perfect A, about 11 percent - or about 471 miles - are failing with a PCI of 40 or below. The 2022-2027 bond program includes $100.5M in funding to reconstruct several so-called F-streets in each council district.
Project Type: Streets, Bridges, & Sidewalks
Status: Construction
Project Contact: Al Siam Ferdous, 210-207-6941
Estimated Construction Timeline: Spring 2023 - Spring 2027
Estimated Construction Timeline Seasons are identified as: Winter (January, February, March), Spring (April, May, June), Summer (July, August, September), and Fall (October, November, December).
Project Budget: | |
2022 General Obligation Bond (Streets) | $ 11,980,000.00 |
Total | $ 11,980,000.00 |
Streets to be reconstructed:
- Florida from S. Pine St. to Dreiss
- Keasler Ave. from Bermuda to McNutt Dr.
- Lake Arbor from Lake Brook to Cul-de-sac
- Macro from NE Loop 410 Access Rd. to Cul-de-sac
- Aspen Farm from Highland Farm to Georges Farm
- Castle Hunt Dr. from Castle Cross to Castle Stream
- Castle Stream from Midcrown Dr. to Castle Hunt Dr.
- Gavlick Farm from Aspen Farm to Brittany Farm
- Goodhue Ave. from Fonville to Glendora
- Heathers Farm from Georges Farm to Juniper Farm
- Highland Farm from Brittany Farm to Lakeview Dr.
- Juniper Farm from Heathers Farm to Aspen Farm
- Elkhorn Dr. from Lanark Dr. to Goodhue Ave.
- Glacier Sun Dr. from Winter Sunrise Dr. to Coral Sunrise
- Hampton St. from Roland Ave. to J St.
- St. Anthony Ave. from Iowa St. to Westfall Ave.
- St. Charles from Burnet St. to Dawson St.
- Industry Park Dr. from Space Center Dr. to Greatfare
- Industry Park Dr. from Rittiman Rd. to Space Center Dr.
- Greatfare from NE Loop 410 Access Rd. to Dead End
- Oakley Farm from Brittany Farm to Aspen Farm
- Rigsby Ave. from Clark Ave. to Amanda
NOTE TO BUSINESS OWNERS:
If your business is currently or expected to experience construction in your area please visit the City of San Antonio's Construction Toolkit. This guide helps business owners understand and prepare for City-initiated construction projects.
Business Outreach Specialist: Monica Cantu, 210-207-3935
Learn more about City projects in your neighborhood and across San Antonio. The City of San Antonio’s digital dashboards encompass a wide range of projects, including streets, drainage, parks, and facilities.