Wurzbach Corridor Sidewalk Project
Wurzbach Corridor Sidewalk Project
The Bond Project includes the construction of pedestrian mobility improvement projects as applicable and within available funding.
Project Type: Streets, Bridges, & Sidewalks
Phase: Construction Phase
Project Budget: $2.35 million
Project Contact: Danielle Monroe, (210) 207-4577
Estimated Construction Timeline: Summer 2024 - Winter 2025
Estimated Timeline Construction Seasons are identified as: Winter (January, February, March), Spring (April, May, June), Summer (July, August, September), and Fall (October, November, December.)
Associated Projects:
Wurzbach at Vance Jackson Intersection Project
Project Limits: Wurzbach Road from Fredricksburg Road to IH-10
NOTE TO BUSINESS OWNERS:
If your business is currently or expected to experience construction in your area please visit the City of San Antonio's Construction Toolkit. This guide helps business owners understand and prepare for City-initiated construction projects.
Business Outreach Specialist: 210-207-3922, [email protected]
Learn more about City projects in your neighborhood and across San Antonio. The City of San Antonio’s digital dashboards encompass a wide range of projects, including streets, drainage, parks, and facilities.
Construction Updates:
- Current Work:
- Phase 3 & 4 Westbound (daytime): The contractor continues concrete work along Wurzbach Road westbound lanes between Datapoint Drive and Dean pannill Drive. Contractor to remove and replace driveways and sidewalk panels that are non-compliant.
- Special Notes:
- There will be lane closures in the area during construction hours. Businesses and their parking lots will remain accessible. There will be intermittent sidewalk closures.
- No parking on Street from 8PM to 7AM
- No parking any time between Bluemel Rd and Fredericksburg Rd.
- Vehicles in the path of the project may be towed to nearby street.
- Work is 7 days a week.
- Hours of Construction:
- DAYTIME- 9AM to 4PM (Phase 4)
- Project Scope:
- Project scope is to improve pedestrian amenities along Wurzbach Road from I-10 to Fredericksburg Road. Improvements include wider sidewalks, improved ADA accessibility, and better access to bus stops as well as utility adjustments.
Contractor preparing to install handrail along Wurzbach Road
Handrail installation along Wurzbach Road near Bluemel Road
Driveway demolition at Kabul International Market
Framework and concrete prep at Wurzbach and Ranchero Road
Contractor working on sidewalk at Wurzbach and Ranchero Road
Project Presentation Documents
Proposed Improvements