Lane closures/Detours:

  • S. Brazos: Detour - 1 day for signs/striping
  • S. Zarzamora: Lane Closure – 2 days for signs/striping and 2 days for concrete work (4 days)
  • Merida: Detour - 1 day for signs/striping
  • Ceralvo: Detour - 1 day for signs/striping and 1 day for concrete work (2 days)
  • Brady: Detour - 1 day for signs/striping

Total working days: 9 days

 

Question title

Would you like to learn more? Sign up here for updates. Feel free to leave a comment, too!

Lane closures/Detours:  S. Brazos: Detour - 1 day for signs/striping S. Zarzamora: Lane Closure – 2 days for signs/striping and 2 days for concrete work (4 days) Merida: Detour - 1 day for signs/striping Ceralvo: Detour - 1 day for signs/striping and 1 day for concrete work (2 days) Brady: Detour - 1 day for signs/striping Total working days: 9 days