2022-2027 Bond Project: District 4 Parks
2022-2027 Bond Project: District 4 Parks
The City of San Antonio's Public Works Department will construct general park and rehabilitation improvements of park facilities within available funding which may include shade enhancements as applicable. Parks may include: Palo Alto Terrace Park, Medina Base Park, Spicewood Park, and Gateway Terrace Park.
Project Type: Parks & Recreation
Phase: Construction
Project Contact: Rekha Shankar - (210) 207-8144
Estimated Construction Timeline: Winter 2026 - Winter 2027
Estimated Timeline Construction Seasons are identified as: Winter (January, February, March), Spring (April, May, June), Summer (July, August, September), and Fall (October, November, December.)
Project Budget: | |
2022 General Obligation Bond (Parks) | $ 1,800,000.00 |
Total | $ 1,800,000.00 |
General Project/COSA Information
What you need to know:
• Ongoing construction on improvements to the following parks, Palo Alto Terrace Park, Gateway Terrace Park, Spicewood Park, and Medina Base Park made possible by the 2022-2027 Bond Program.
• Project Timeline: Winter 2026 - Winter 2027
Estimated Timeline Construction Seasons are identified as: Winter (January, February, March), Spring (April, May, June), Summer (July, August, September), and Fall (October, November, December.)
Palo Alto Terrace Park includes a basketball shade structure, lighting, concrete base resurfacing and landscaping.
Gateway Terrace Park consists of a basketball shade structure, lighting, and new concrete walkway connection from the street.
Spicewood Park adds a playground shade structure, basketball shade structure, lighting, and landscaping.
Medina Base Park involves a skate park renovation, a dog park with shade structure and amenities, basketball shade structure, lighting, concrete base resurfacing and landscaping.
Site Closures: Playground and basketball courts
• Palo Alto Terrace Park: Week of 08/24 - 8/31
• Gateway Terrace Park: Week of 08/31 - 9/7
• Spicewood Park: Week of 09/07 - 9/14
• Medina Base Park: Week of 09/14 - 9/21
Palo Alto Terrace Park Map
Gateway Terrace Park Map
Spicewood Park Map
Medina Base Park Map
Please share any feedback or questions about this project.
NOTE TO BUSINESS OWNERS:
If your business is currently or expected to experience construction in your area please visit the City of San Antonio's Construction Toolkit. This guide helps business owners understand and prepare for City-initiated construction projects.
Learn more about City projects in your neighborhood and across San Antonio. The City of San Antonio’s digital dashboards encompass a wide range of projects, including streets, drainage, parks, and facilities.
Project Presentation Documents