2022-2027 Bond Project: Gardendale Street & Drainage (Wurzbach Road to Bluemel Road)

2022-2027 Bond Project: Gardendale Street & Drainage (Wurzbach Road to Bluemel Road)

Phase: Design Phase

Project Contact: Tania Mendoza - (210) 207-6905 - tania.mendoza@sanantonio.gov

Estimated Construction Timeline: Summer 2026 - Summer 2027

Estimated Timeline Construction Seasons are identified as: Winter (January, February, March), Spring (April, May, June), Summer (July, August, September), and Fall (October, November, December.)


Streets-The Bond Project will construct roadway improvements to include sidewalks, curbs, driveway approaches, drainage and other improvements as applicable and within available funding.

Project Type: Streets, Bridges, & Sidewalks

Project Budget: (Streets)

 

2022 General Obligation Bond (Streets)   $3,000,000.00

         

CPS Energy                                              $50,000.00

             

San Antonio Water System                       $68,325.00

             

Total                                                         $3,118,325.00

        

Drainage-The Bond Project will install an underground storm drain system which may include associated roadway reconstruction, curbs, sidewalks, and driveway approaches as applicable and within available funding.

Project Type: Drainage and Flood Control

Project Budget: (Drainage)

 

2022 General Obligation Bond (Drainage)  $3,360,000.00

        

CPS Energy                                                 $67,464,06

          

San Antonio Water System                         $50,000.00  

        

Total                                                           $3,477,464.06

       


Project Limits:

What you need to know

 

Global Contractors, LLC will begin construction of essential underground storm drain repairs and utility upgrades. As early as Sept. 4, 2026, the contractor will begin moving equipment into the area and setting up construction signs and traffic barriers.

 

Phase 0 & 1 - Storm Drain Repairs: As early as Sept 14 through mid-December 2026, crews will begin with underground storm drain repairs on Wurzbach Rd. near the Gardendale Rd. intersection and will start removing old pavement in preparation to install a new CPS Energy gas line along the southbound lane on Gardendale Rd

 

Traffic Impact

  • Expect occasional, short-term lane closures on the eastbound lane of Wurzbach Rd. near the Gardendale Rd. intersection.
  • One lane of Gardendale Road will be closed, however, two-way traffic will remain open throughout phases 0 & 1.

All local businesses will remain accessible at all times.

 

Gardendale St. - Phase 0 & 1

 

Gardendale St. - Phase 0 & 1

 

 

Overall Project Information

 

This Bond Project will construct a three-lane roadway and install an underground storm drain system. Additional improvements include a wider sidewalk on the north side of the street, a shared-use path on the south side, new curbs, updated driveway approaches, and utility relocations.

 

Gardendale - South view

Gardendale - South view

Gardendale - North view

Gardendale - North view

 


NOTE TO BUSINESS OWNERS:

If your business is currently or expected to experience construction in your area please visit the City of San Antonio's Construction Toolkit. This guide helps business owners understand and prepare for City-initiated construction projects.


Learn more about City projects in your neighborhood and across San Antonio. The City of San Antonio’s digital dashboards encompass a wide range of projects, including streets, drainage, parks, and facilities.


 

Contact Information

To receive project updates and details on future public meetings, please provide the following information.

Please share any feedback or questions about this project.