2017-2022 Bond Project: South Alamo Street (Market Street to East Cesar E. Chavez Blvd.)
2017-2022 Bond Project: South Alamo Street (Market Street to East Cesar E. Chavez Blvd.)
This Bond Project will reconstruct Alamo St. from Market to Cesar E. Chavez. Includes pedestrian amenities and enhancements as appropriate and within available funding.
Project Type: Streets
Phase: Construction
Project Contact: Joey Doctor, (210) 207-8415
Estimated Construction Timeline: Fall 2022 - Spring 2026
Estimated Timeline Construction Seasons are identified as: Winter (January, February, March), Spring (April, May, June), Summer (July, August, September), and Fall (October, November, December.)
Project Budget:
| TOTAL | $ 58,941,935.82 | ||
| 2017 GO Bond - Streets | $ 20,561,541.00 | ||
| AT&T Contribution | $ 1,500,556.00 | ||
| CPS Contribution | $ 2,028,308.22 | ||
| SAWS Contribution | $ 16,034,725.47 | ||
| TIRZ | $ - | ||
| Tree Mitigation Fund | $ 750,000.00 | ||
| Unissued Certificates of Obligation | $ 18,066,805.13 |
* The Bond Dashboard is pending scheduled updates.
Project Limits:
Know Before You Go Downtown! Plan ahead for traffic, detours and parking at this link: https://saspeakup.com/downtown
SUPPORT YOUR LOCAL SMALL BUSINESSES: https://www.sanantonio.gov/EDD/Programs-Grants/Paving-The-Way
NOTE TO BUSINESS OWNERS:
If your business is currently or expected to experience construction in your area please visit the City of San Antonio's Construction Toolkit. This guide helps business owners understand and prepare for City-initiated construction projects.
Business Outreach Specialist: Gabby Tello, 210-207-4688
Learn more about City projects in your neighborhood and across San Antonio. The City of San Antonio’s digital dashboards encompass a wide range of projects, including streets, drainage, parks, and facilities.
What you need to know:
Nueva at South Alamo – Southwest Lane Closure
- Beginning as early as Monday, November 3, 2025 there will be no eastbound right turn onto South Alamo due to the Nueva at South Alamo southwest lane closure.
- Access to Nueva provided from South Presa and closed to thru traffic.
- See map provided
South Alamo Traffic Switch
- Beginning as early as Monday, November 3, 2025 the contractor will switch traffic on South Alamo from Nueva to Cesar Chavez to the center lane.
- The eastside sidewalks will be reopening along Hemisfair, and the westside sidewalks will be closed.
- See map provided
South Alamo Overnight Work
- Beginning as early as Tuesday, November 4, 2025 thru Thursday, November 6, 2025, the contractor will fully close vehicular and pedestrian access between the hours of 10:00pm to 6:00am each day on South Alamo between the Hilton Palacio Del Rio Hotel driveways
- Each morning South Alamo will have a single southbound traffic lane open
- This work is necessary to allow the completion of the utility conduit for the Monarch Hotel
- To facilitate access for hotel guests and valet service for the hotels, police officers will be available at Market Street & South Alamo intersection. See map provided
Overall Project Information
- Reconstruction work continues on South Alamo (Market Street to Cesar Chavez). See map provided
- South Alamo continues to have a single southbound traffic lane open
- Nighttime concrete pours on South Alamo continues in October 2025 and November 2025
- Cesar Chavez traffic lanes are open
- Business access, parking lot and pedestrian access provided
South Alamo - Reconstruction Map with Detours
Overnight Work Map
Businesses remain open and accessible!
BUY LOCAL!