2017-2022 Bond Project: District 1 Pedestrian Mobility & Streets
2017-2022 Bond Project: District 1 Pedestrian Mobility & Streets
The Bond Project will construct pedestrian mobility and street improvement projects.
Project Type: Streets, Bridges & Sidewalks
Phase: Construction
Project Contact: Roxana Garcia - (210) 207-1461
Estimated Construction Timeline: Summer 2018-Spring 2025
Estimated Timeline Construction Seasons are identified as: Winter (January, February, March), Spring (April, May, June), Summer (July, August, September), and Fall (October, November, December.)
Project Budget: |
| ||
2017 General Obligation Bond (Street) | $9,000,000.00 | ||
Citywide Pedestrian Improvements | $1,936,000.00 | ||
Great American Insurance | $407,132.39 | ||
San Pedro Pedestrian Improvements | $499,757.66 | ||
San Antonio Water System | $298,975.00 |
Total | $12,141,865.05 |
Associated Projects:
- N. St. Mary's Street (Mistletoe to East Mulberry) – Currently in design. Anticipated design completion date Summer 2024. Construction scheduled for Fall 2024.
- Fresno Phase II (Fredericksburg to Excelsior Dr) - Currently in design. Anticipated design completion date Fall 2024. Construction scheduled for Summer 2025.
Project Limits: Fredericksburg (IH-10 to Balcones Heights) Phase
NOTE TO BUSINESS OWNERS:
If your business is currently or expected to experience construction in your area please visit the City of San Antonio's Construction Toolkit. This guide helps business owners understand and prepare for City-initiated construction projects.
Business Outreach Specialist: 210-207-3922, [email protected]
Learn more about City projects in your neighborhood and across San Antonio. The City of San Antonio’s digital dashboards encompass a wide range of projects, including streets, drainage, parks, and facilities.
PROJECT UPDATE 2/26/24:
TEMPORARY ROAD CLOSURE: Louise St. at Fredericksburg Rd will be closed for the duration of the project.
- Accessibility to Louise St. will be maintained for residents and businesses at W. Summit Ave.
- Partial lane closures will be in place throughout the duration of the project.