Estimated Construction Timeline

Lane closures/Detours:

  • Toepperwein: Lane closure - 1 day for signs/striping
  • Thousand Oaks: Lane closure - 1 day for signs/striping
  • Whirlwind: Detour - 1 day for signs/striping
  • Leonhardt: Detour – 1 day for signs and striping and Lane Closure – 1 day for concrete work (2 days)

Total working days: 5 days

 

 

Question title

Would you like to learn more? Sign up here for updates. Feel free to leave a comment, too!

Lane closures/Detours:  Toepperwein: Lane closure - 1 day for signs/striping Thousand Oaks: Lane closure - 1 day for signs/striping Whirlwind: Detour - 1 day for signs/striping Leonhardt: Detour – 1 day for signs and striping and Lane Closure – 1 day for concrete work (2 days) Total working days: 5 days