2022-2027 Bond Project: Peggy Drive Area Drainage (Eastgate Subdivision)
2022-2027 Bond Project: Peggy Drive Area Drainage (Eastgate Subdivision)
The Project will complete the regrading of an existing earthen channel and installation of an underground storm drain system and associated reconstruction of streets with curbs, sidewalks, and driveway approaches as applicable and within available funding.
Project Type: Drainage and Flood Control
Phase: Construction
Project Contact: Florencio Rodriguez, (210) 207-3966
Estimated Construction Timeline: Summer 2026 - Winter 2028
Estimated Timeline Construction Seasons are identified as: Winter (January, February, March), Spring (April, May, June), Summer (July, August, September), and Fall (October, November, December.)
Project Budget: | |
2022 General Obligation Bond (Drainage) | $20,000,000.00 |
San Antonio Water System | $5,017,743.89 |
Total | $25,017,743.89 |
Project Limits
What you need to know:
Contractors will begin activities as early as July 6, 2026, thru February 2027 with the following work:
- Clearing and preparing the natural drainage channel south of Eunice Street.
- Adjusting underground water & sewer lines and relocating fire hydrants.
- Installing of new storm drainage along Peggy Dr., Stutts Dr. and Eunice Street intersections
Traffic & Detour Information:
- Eunice Street between Peggy Dr. and Stutts Dr. will be closed to traffic starting as early as July 6, 2026, thru February 2027.
- Detour route will be available. See map provided.
Detour Map
NOTE TO BUSINESS OWNERS:
If your business is currently or expected to experience construction in your area please visit the City of San Antonio's Construction Toolkit. This guide helps business owners understand and prepare for City-initiated construction projects.
Learn more about City projects in your neighborhood and across San Antonio. The City of San Antonio’s digital dashboards encompass a wide range of projects, including streets, drainage, parks, and facilities.
Please share any feedback or questions about this project.
Project Presentation Documents
Proposed Improvements
Tie into Phase 1 Drainage Channel