Construction Update:

 

Bridge Closure & Bridge Repair Work

Public Works along with EZ-Bel Construction will be commencing construction repairs for the Citywide Three Historical Bridge Rehabs (Augusta St, Crockett St., and South Presa St. Bridges over the San Antonio River)​ Project.

 

The work to be done includes the following Bridge Closure & Bridge Repair Work:

South Presa Street Bridge over the San Antonio River : Construction Starts: 10.2.23 thru 10.23.23. 

Crockett Street Bridge over the San Antonio River: Construction Starts: 10.24.23 thru 11.3.23. 

Augusta Street Bridge over the San Antonio River: Construction Starts: 11.3.23 thru 11.20.23. 

Due to weather conditions or unforeseen occurrences the closure date may be adjusted.

 

We sincerely appreciate your patience and cooperation while these improvements are in progress. While improvements are underway, here is some helpful information about the improvement project to assist you:

  • Vehicles should not be parked on the street. If vehicles are in the path of the project and no one is available to move it, it will be towed to one of the streets in your area.
  • Traffic detour barricades and signs will be provided to guide traffic through the construction as needed.
  • Sidewalks on the Riverwalk level will be opened in the afternoon for full pedestrian access.
  • In the event of adverse weather, environmental conditions, unforeseen equipment issues, or schedule conflicts, work will likely be rescheduled as soon as conditions permit. 
  • See detour maps below:

 

South Presa Street Bridge

 

Crockett Street Bridge

 

Augusta Street Bridge

 