Project Update: December 22, 2023

 

WORK COMPLETED IN THE LAST 2 WEEKS: (From Abshire to east of 36th St.)

  • Milled asphalt to new elevations on the south side of roadway
  • Final Asphalt placed on the south side of the roadway
  • Asphalt placed behind sidewalk
  • Z crossing median west of 39th St.

 

PLANNED UPCOMING ACTIVITIES:

  • Mill asphalt to new elevation on the north side of roadway
  • Place final asphalt and Concrete on the north side of the roadway and behind sidewalk
  • Pedestrian signal work at 36th St.
  • Project completion late January/mid Feruary 2024

 

New Street Name

 

At 39th Street Looking East

 

At Cesar Chavez Looking West

 

Milling on the North Side of Roadway

 

Z Crossing Median

 


 

Question title

To receive project updates and details on future public meetings, please provide the following information.

Question title

Please share any feedback or questions about this project.

PROPOSED IMPROVEMENTS

Rendering Below: Pedestrian 'Z Crossing' making it safer to cross the width of the highway.