2022-2027 Bond Project: North New Braunfels Avenue Phase 2 (East Houston Street to Paso Hondo Street)
2022-2027 Bond Project: North New Braunfels Avenue Phase 2 (East Houston Street to Paso Hondo Street)
The Bond Project will construct roadway improvements to include sidewalks, driveway approaches, trees and irrigation, as well as joint bid utility work including valve adjustments, manhole reconstruction, and other improvements as applicable and within available funding.
Project Type: Streets, Bridges, & Sidewalks
Phase: Construction
Project Contact: Tania Mendoza - (210) 207-6905
Estimated Construction Timeline: Winter 2025 - Winter 2026
Estimated Timeline Construction Seasons are identified as: Winter (January, February, March), Spring (April, May, June), Summer (July, August, September), and Fall (October, November, December.)
Related Project: 2017-2022 Bond Project: North New Braunfels Ave Phase 1 (E Houston St to Burleson St)
Project Budget: | |
2022 General Obligation Bond (Streets) | $ 6,500,000.00 |
San Antonio Water System | $ 249,177.00 |
Tree Preservation Fund | $ 325,000.00 |
Total | $ 7,074,177.00 |
Project Limits:
Construction update: March 25, 2025
North New Braunfels - Lane closures and detours
Contractor J3 Construction Company will start performing work on sidewalks, curbs and driveway approaches on the east side of N. New Braunfels between East Houston and Canton Street as early as March 28, 2025, weather permitted. Traffic and pedestrian control plan will be as follows:
- Two travel lane closures for northbound traffic will be necessary to perform the work through April 2025.
- East sidewalk closed to pedestrians.
- Two southbound travel lanes will be open to traffic.
- West side sidewalk will be open to pedestrians.
- Side streets and its sidewalks will be open at all times.
- Businesses will have full access to costumers.
- Vehicular detours to alleviate traffic (see map provided).
We appreciate your patience, and please slow down for all construction activities.
Thank you.
North New Braunfels - Northbound Lanes Closure
Curb and sidewalk work on the west side of N. New Braunfels Ave.
Curb, sidewalk and driveway construction on the west side of N. New Braunfels Ave.
Curb and sidewalk under construction on the west side of N. New Braunfels Ave.
--------------------------------------------------------------------------------------------------------------------------------------------
Construction Update: 2.21.25
North New Braunfels - Southbound Lane Closure
Contractor J3 Construction Company will be performing work on sidewalks, curbs, driveway approaches, and utility work on North New Braunfels starting as early as Thursday, February 27, 2025. A lane closure for southbound traffic on North New Braunfels between East Houston Street and Paso Hondo will be necessary to perform the work thru April 2025. To facilitate traffic one southbound traffic lane will always be open, and two northbound traffic lanes will be open. Sidewalk, driveways, and parking lot access will be maintained for all businesses. All side streets will remain open and accessible. All work is weather permitting. Please see the map provided.
We appreciate your patience, and please slow down for all construction activities. Thank you.
North New Braunfels Southbound Lane Closure
Construction Update:
North New Braunfels - Northbound Lane Closure
Contractor J3 Construction Company will be performing work on sidewalks, curbs, and driveway approaches on North New Braunfels starting as early as Thursday, January 23rd, 2025. A lane closure for northbound traffic on North New Braunfels between Houston Street and Paso Hondo will be necessary to perform the work through March 2025. To facilitate traffic one northbound traffic lane will always be open, and two southbound traffic lanes will be open. Sidewalk, driveways, and parking lot access will be maintained for all businesses. All side streets will remain open and accessible. All work is weather permitting and subject to change. Please see the map provided. We appreciate your patience, and please slow down for all construction activities.
Thank you.
North New Braunfels - Northbound Lane Closure
Construction Update:
North New Braunfels – Southbound Lane Closure
Contractor J3 Construction Company will be performing utility work on North New Braunfels starting as early as Tuesday, January 21, 2025. A lane closure for southbound traffic on North New Braunfels between Houston Street and Paso Hondo will be necessary to perform the work thru March 2025. To facilitate traffic one southbound traffic lane will always be open, and two northbound traffic lanes will be open. Sidewalk, driveways, and parking lot access will be maintained for all businesses. All side streets will remain open and accessible. All work is weather permitting. Please see the map provided. We appreciate your patience, and please slow down for all construction activities. Thank you.
North New Braunfels - Southbound Lane Closure
Construction Notice:
Design Update:
The City investigated safety concerns at the intersection of N New Braunfels Avenue and Canton St that were mentioned during the public meeting held in January, 2024. To enhance safety at this intersection, the City will include the installation of a dedicated left turn and a turnaround at Canton Street along with a new mid-block crossing. These changes will promote safer driving conditions and improve pedestrian safety in this corridor. Please see the Proposed Median Improvements exhibit provided.
Proposed Median Improvements
SUPPORT YOUR LOCAL SMALL BUSINESSES: https://www.sanantonio.gov/EDD/Programs-Grants/Paving-The-Way
NOTE TO BUSINESS OWNERS:
If your business is currently or expected to experience construction in your area please visit the City of San Antonio's Construction Toolkit. This guide helps business owners understand and prepare for City-initiated construction projects.
Business Outreach Specialist: Monica Cantu, 210-207-3935
Learn more about City projects in your neighborhood and across San Antonio. The City of San Antonio’s digital dashboards encompass a wide range of projects, including streets, drainage, parks, and facilities.
Project Presentation Documents
Existing Conditions