2022-2027 Bond Project: Port San Antonio Area Streets
2022-2027 Bond Project: Port San Antonio Area Streets
The Project will construct roadway improvements at Port San Antonio to include sidewalks, curbs, driveway approaches, drainage, and other improvements as applicable and within available funding. This is a multi-phased project. Roadways may include: Billy Mitchell Boulevard, General McMullen and General Hudnell.
Project Type: Streets, Bridges, & Sidewalks
Phase: Design Phase
Project Contact: Joe Garcia - (210) 207-0097
Estimated Construction Timeline: Winter 2025-Spring 2028
Estimated Timeline Construction Seasons are identified as: Winter (January, February, March), Spring (April, May, June), Summer (July, August, September), and Fall (October, November, December.)
Project Budget: | |
2022 General Obligation Bond (Streets) | $15,000,000.00 |
Tree Preservation Fund | $750,000.00 |
Total | $15,750,000.00 |
Project Limits:
NOTE TO BUSINESS OWNERS:
If your business is currently or expected to experience construction in your area please visit the City of San Antonio's Construction Toolkit. This guide helps business owners understand and prepare for City-initiated construction projects.
Business Outreach Specialist: 210-207-3922, [email protected]
Learn more about City projects in your neighborhood and across San Antonio. The City of San Antonio’s digital dashboards encompass a wide range of projects, including streets, drainage, parks, and facilities.
Project Presentation Documents
Proposed Improvements