2022-2027 Bond Project: District 5 Pedestrian Mobility
2022-2027 Bond Project: District 5 Pedestrian Mobility
The Bond Project will construct pedestrian mobility improvement projects as applicable and within available funding.
Project Type: Streets, Bridges, & Sidewalks
Phase: Construction
Project Contact: John Harris - (210) 973-1694
Estimated Construction Timeline: Summer 2024 - Spring 2027
Estimated Construction Timeline Seasons are identified as: Winter (January, February, March), Spring (April, May, June), Summer (July, August, September), and Fall (October, November, December).
Associated Projects:
- S. Leona Street (San Fernando to El Paso)
- Paseo Verde (S. Leona to Dead-end)
- Patton (34th Street to 35th Street)
- S Trinity Blvd (Frio City Road to Mercedes)
- Kirk (Dead-end to Nogalitos)
- Barrett Place (Niemeyer to Carolyn Street)
- Barrett Place (S. Zarzamora to Nogalitos)
- Carroll Avenue (S. Zarzamora to Nogalitos)
PROJECT UPDATE: D5 SIDEWALKS KIRK PL, 1st phase (UPRR dead-end to DESOTO) completed,
Construction scheduled to begin Winter 2025 with an estimated completion Spring 2025
Project Budget: | |
2022 General Obligation Bond (Streets) | $3,000,000.00 |
SAWS Contribution $55,025.00
Total | $3,055,025.00 |
NOTE TO BUSINESS OWNERS:
If your business is currently or expected to experience construction in your area please visit the City of San Antonio's Construction Toolkit. This guide helps business owners understand and prepare for City-initiated construction projects.
Business Outreach Specialist: Monica Cantu, 210-207-3935
Learn more about City projects in your neighborhood and across San Antonio. The City of San Antonio’s digital dashboards encompass a wide range of projects, including streets, drainage, parks, and facilities.