2022-2027 Bond Project: Sonterra Rd. Ext. (Sonterra to Loop 1604)
2022-2027 Bond Project: Sonterra Rd. Ext. (Sonterra to Loop 1604)
The Project will construct roadway improvements to include sidewalks, curbs, driveway approaches, drainage, and other improvements as applicable and within available funding.
Project Type: Streets
Phase: Construction
Project Contact: Betsy Hove - (210) 207-7787
Estimated Construction Timeline: Summer 2024 - Summer 2025
Estimated Timeline Construction Seasons are identified as: Winter (January, February, March), Spring (April, May, June), Summer (July, August, September), and Fall (October, November, December.)
Project Budget: CPS Contribution SAWS Contribution $141,057.88 | $155,550.00 |
2022 General Obligation Bond (Streets) | $6,000,000.00 |
Total | $6,296,607.88 |
Project Limits:
Construction Updates:
Construction Update October 3, 2024 - Sonterra Road Extension (Sonterra Road to Loop 1604)
Construction began on Monday, August 5 on a project to add lanes, curbs and a raised center median with lighting. Upon completion of the project there will also be shared-use paths for pedestrians, utility adjustments and drainage improvements.
- Construction started on Sonterra Road where it ends just before the Community Bible Church driveway.
- Current Phase I Work: Roadway grading and site preparation is ongoing. Contractor has started installation of the proposed storm sewer system. Contractor completed SAWS water line relocation and tie-in.
- Current Phase II & III Work: Roadway grading and site preparation is ongoing.
- Northern Community Bible Church driveway continues to be closed during Phase I construction.
- The Gold Canyon Driveway continues to be open.
NOTE TO BUSINESS OWNERS:
If your business is currently or expected to experience construction in your area please visit the City of San Antonio's Construction Toolkit. This guide helps business owners understand and prepare for City-initiated construction projects.
Learn more about City projects in your neighborhood and across San Antonio. The City of San Antonio’s digital dashboards encompass a wide range of projects, including streets, drainage, parks, and facilities.
Project Presentation Documents