2017-2022 Bond Project: District 6 Pedestrian Mobility & Streets
2017-2022 Bond Project: District 6 Pedestrian Mobility & Streets
The Bond Project will construct pedestrian mobility and street improvement projects.
Project Type: Streets, Bridges & Sidewalks
Phase: Construction
Project Contact: Grace Gonzalez, (210) 207-2776
Estimated Construction Timeline: Spring 2019-Spring 2025
Estimated Timeline Construction Seasons are identified as: Winter (January, February, March), Spring (April, May, June), Summer (July, August, September), and Fall (October, November, December.)
Associated Projects:
- W. Commerce Street at LBJ Elementary School – Pedestrian signalized crossing; Construction began 2/13/24; Installation scheduled for August 2024.
- Castroville Road at Henry B. Gonzalez Elementary School - Pedestrian signalized crossing; Construction began 2/13/24; Installation scheduled for August 2024.
- Westshire Dr (Rawhide Dr to Westvale Dr) – Design complete. Moved to 2022 Ped Mobility Bond for construction.
- Castroville Road (South of Callaghan to Acme Road) – Postponed to Summer 2024
- Andros Place (Marimba Pl to Westward)
- Barbardos (Westward to Marimba Pl)
- Brandyridge (Weybridge to Woodtrail)
- Marimba Pl (Barbados to Andros Pl)
- Pipers Lane (Culebra Road to Dead End)
- Spiral Creek (Creek Ridge to Creek Run)
- Split Creek (Sparrow Creek to Tumbling Water)
- Timber Fern (Timber Glen to Timber Basin)
- Westmoor (Westlyn to Westbriar)
- Westoak Drive (Westrock Dr to Westfield Dr)
- Westward (Pinn Road to Andros Pl)
- Windward Way (Barbados to Andros Place)
Project Budget: | |
2017 General Obligation Bond (Street) | $5,000,000.00 |
San Antonio Water System | $178,650.00 |
Total | $5,178,650.00 |
NOTE TO BUSINESS OWNERS:
If your business is currently or expected to experience construction in your area please visit the City of San Antonio's Construction Toolkit. This guide helps business owners understand and prepare for City-initiated construction projects.
Business Outreach Specialist: Jonathan Gasper, 210-207-6055
Learn more about City projects in your neighborhood and across San Antonio. The City of San Antonio’s digital dashboards encompass a wide range of projects, including streets, drainage, parks, and facilities.