2017 - 2022 Bond: Prue Road (Babcock Road to Laureate Drive) (D/B)
2017 - 2022 Bond: Prue Road (Babcock Road to Laureate Drive) (D/B)
The Bond Project will reconstruct Prue Road from Babcock Road to Laureate Drive. The project construction will include curbs, 10-foot shared use path for bicycles and pedestrians on the north side and a 6-foot sidewalk on the south side, new driveway approaches, signal improvements, and underground drainage.
Project Type: Streets
Phase: Construction
Project Contact: Danielle Monroe - (210) 207-4577
Estimated Construction Timeline: Winter 2021 - Spring 2025
*The City is actively working with the contractor on a schedule recovery plan. We will keep you posted on updates to the construction finish.
Estimated Timeline Construction Seasons are identified as: Winter (January, February, March), Spring (April, May, June), Summer (July, August, September), and Fall (October, November, December.)
Project Budget: |
| ||
2007 General Obligation Bond (Drainage) | $34,982.89 | ||
2012 General Obligation Bond (Drainage) | $3,919,747.48 | ||
2012 General Obligation Bond (Street) | $1,045,269.63 | ||
2017 General Obligation Bond (Street) | $27,600,000.00 | ||
CPS Energy | $3,294,996.52 | ||
Grey Forest Utilities Contribution | $600,000.00 | ||
San Antonio Water System | $3,784,895.25 |
Total | $40,279,891.77 |
PROJECT UPDATE:
We are nearing substantial completion on Prue Road, but due to some unforeseen weather delays in January still have items to complete and are working hard to move toward completion with some of the final items remaining.
Striping of the lanes is complete, and our main focus is now on completion of the Shared Use Path and the remaining driveways. The contractor is about 90% complete with installation of the 5 x 4 storm drain boxes, and close to tying in with Prue Road. We anticipate that will will be done with these items in mid to late April.
Our current estimate for completion remains early 2025.
Please note, although we have rain projected for this week, the drainage system is not complete and finalized or tied in with Prue Road at this time. You will see a fully functioning response to the drainage from the new project once all work is complete.
PLANNED UPCOMING ACTIVITIES:
- May 21, 2025 - end of May:
- JDA complete with final striping
- May 21, 2025 - mid April, 2025:
- Fox Quality Concrete working on shared use path, curb walls, curb ramps, driveways and median curbs between Woodridge and Laureate
- Fox Quality Concrete will begin textured concrete and inlet riprap
- May 21, 2025 - mid April:
- JDA finalizing construction of right turn lane at Prue and Laureate
Contractor measuring for striping at intersection of Prue Road and Southwell Road
Prue Road facing east, new median and centerline striping, new shared use path
**PLEASE NOTE: ALL WORK IS SUBJECT TO FAVORABLE WEATHER CONDITIONS**
NOTE TO BUSINESS OWNERS:
If your business is currently or expected to experience construction in your area please visit the City of San Antonio's Construction Toolkit. This guide helps business owners understand and prepare for City-initiated construction projects.
Business Outreach Specialist: 210-207-3922, [email protected]
Learn more about City projects in your neighborhood and across San Antonio. The City of San Antonio’s digital dashboards encompass a wide range of projects, including streets, drainage, parks, and facilities.
Roller compacting asphalt behind paving machine near Venado Trace on North side of Prue Road
Excavation work, curb walls, curb ramps and bus pad installation vicinity Network to Laureate
Asphalt paving work on the north side of Prue Road looking East