Project Update: July 26, 2024
 

PLANNED UPCOMING ACTIVITIES:

  • 7/24/2024 - 7/31/2024: 
    • JDA will continue  drainage lateral construction System A Babcock to Huebner Creek.
  • 7/24/2024 - 7/31/2024: 
    • JDA will continue working on road excavation and grading and begin flexible base placement on the North Side of the project from Babcock Rd to Venado Trace.

                                                                                        

  • 7/24/2024 - 7/31/2024: 
    • Fox Concrete will continue to work on curb wall and sidewalk on the south side of the project.
  • 7/24/2024 - 8/07/2024:
    • JDA will be working on Road Excavation and flex base pavement on the North Side of the project from Venado Trace to Oakland Rd.

 

                                                                                        

  • 7/24/2024 - 7/31/2024: 
    • Fox concrete will continue to work on curb wall, sidewalk on the south side of the project.
  • 7/24/2024 - 8/07/2024:
    • ​JDA will be working on road excavation and flex base placement on the North Side of the Project from Oakland Rd. to Laureate.
  • 7/24/2024 - 7/31/2024: 
    • JDA will continue on drainage lateral systems C and D from East of Oakland to Laureate.

                                                                                        

  • 7/24/2024 - 7/31/2024:
    • ​ATT continues adjusting duct bank on Network and Prue Rd.

 

                                                                                    

  • 7/29/2024: 
    • Outfall C drainage continues from just south of Lockhill north toward Prue Rd.
    • Outfall C drainage continues between Verbena and Hollyhock.
  • 7/29/2024:
    • ​Lockhill closes to through traffic between Southwell and Oakland - for drainage construction. Detour via Prue Rd or Hollyhock.

                                                                                    

Project Update: July 12, 2024
 

PLANNED UPCOMING ACTIVITIES:

 

                                                                                        

  • 7/10/2024 - 7/17/2024: 
    • JDA will continue  drainage lateral construction System A Babcock to Hueber Creek.
  • 7/10/2024 - 7/24/2024: 
    • JDA will continue working on Road Excavation and grading and begin Flexible base placement on the North Side of the project from Babcock Rd to Venado Trace.

 

 

 

                                                                                        

  • 7/10/2024 - 7/17/2024: 
    • Fox concrete will continue to work on curb wall, sidewalk on the south side of the project.
  • 7/10/2024 - 7/24/2024: 
    • JDA will be working on Road Excavation and flex base placement on the North Side of the project from Venado Trace to Oakland Rd. 

 

 

                                                                                        

  • 7/10/2024 - 7/17/2024: 
    • Fox concrete will continue to work on curb wall, sidewalk, and driveways on the south side of the project.
  • 7/10/2024 - 7/24/2024: 
    • JDA will be working on road excavation and flex base placement  on the North Side of the project from Oakland Rd. to Laureate.
    • JDA will continue on drainage laterals systems C and D from East of Oakland to Laureate. 

 

 

 

                                                                                    

  • 7/10/2024 - 7/17/2024: 
    • Miller Bros working on the 12" WL installation  from Sta 79+04 to 87+56 doing testing, chlorination and tie ins.
  • 7/10/2024 - 7/17/2024: 
    • ATT adjusting Duct Bank on Network and Prue Rd.

                                                                                    

  • 7/22/2024: 
    • Outfall C drainage continues from just south of Lockhill north toward Prue Rd.
    • Outfall C drainaged continues between Verbena and HollyHock.
  • 7/29/2024: 
    • Lockhill closes to Thru Traffic between Southwell and Oakland - for drainage construction. Detour via Prue Rd or HollyHock.

 

Project Update:  June 28, 2024

PLANNED UPCOMING ACTIVITIES:

 

  • 6/26/2024 - 7/05/2024: 
    • JDA will continue  drainage lateral construction System A Babcock to Hueber Creek.
  • 6/26/2024 - 7/05/2024: 
    • JDA will be working on Road Excavation and grading and begin Flexible base placement   on the North Side of the project from Babcock Rd to Venado Trace.

 

 

  • 6/26/2024 - 7/05/2024: 
    • Fox concrete will continue to work on curb wall, sidewalk on the south side of the project. 6-26-24 to 7-05-24.
  • 6/26/2024 - 7/10/2024: 
    • JDA will be working on Road Excavation and flex base placement on the North Side of the project from Venado Trace to Oakland Rd. 6-26-24 to 7-10-24. 

 

 

  • 6/26/2024 - 7/10/2024: 
    • Fox concrete will continue to work on curb wall, sidewalk, and driveways on the south side of the project. 
    6/26/2024 - 7/10/2024: 
    • JDA will continue on drainage laterals systems C and D from East of Oakland to Laureate. 
  • 6/26/2024 - 7/10/2024: 
    • JDA will be working on road excavation and flex base placement  on the North Side of the project from Oakland Rd. to Laureate. 

 

 

  • 6/26/2024 - 7/05/2024: 
    • Miller Bros working on the 12" WL installation  from Sta 79+04 to 87+56 doing testing, chlorination and tie ins.
  • 6/26/2024 - 7/10/2024: 
    • ATT adjusting Duct Bank on Network and Prue Rd

 

 

  • 7/08/2024: 
    • Outfall C drainage continues between Verbena and HollyHock.
  • 7/15/2024: 
    • Lockhill closes to Thru Traffic between Southwell and Oakland - for drainage construction. Detour via Prue Rd or HollyHock.
    • Outfall C drainage continues from just south of Lockhill north toward Prue Rd.

 

 

Project Update:  May 30, 2024

PLANNED UPCOMING ACTIVITIES:

 

 

 

  • 5/30/2024 - 6/07/2024: 
    • AT&T will continue lowering duct bank work at Jade Heights.
  • 5/30/2024 - 6/13/2024: 
    • JDA will be working on road excavation and grading on the north side of the project from Babcock Rd to Venado Trace.
    • JDA will start drainage lateral construction Sytem A Babcock to Hueber Creek. 

 

 

 

  • 5/30/2024 - 6/13/2024: 
    • Fox concrete will continue to work on curb wall, sidewalk on the south side of the project.
    • JDA will be working on road excavation on the north side of the project from Vendado Trace to Oakland Rd.
    • JDA will be working on removal of driveways, curb and sidewalk on the north side of the project from Venado Trace to Oakland Rd. 
    • JDA will start drainage lateral construction system B Huebner Creek to east of Oakland Rd. 

 

 

 

  • 5/30/2024 - 6/13/2024: 
    • Fox concrete will continue to work on curb wall, sidewalk on the south side of the project.
    • JDA will be working on grading for sidewalk, curb wall and installation of railing on the south side of the project. 
    • JDA will be working on Road Excavation on the north side of the project from Oakland Rd. to Network Blvd. 

 

 

  • 6/03/24 - 6/13/2024:
    • Miller Bros will continue working on the north side of the project starting at Network Blvd.  They will install fire hydrants, hydrostatic and chlorination test, 3 tie ins. 
    • Miller Bros will start working on the 12" WL from Sta 79+04 to 87+56. 

 

 


 

 

Project Update:  May 17, 2024

PLANNED UPCOMING ACTIVITIES:

 

  • 5/16/24 - Verbena Road will reopen. 

 

 

  • 5/16/2024 - 5/30/2024: 
    • AT&T will begin work at Jade Heights.
    • JDA will be working on road excavation on the north side of the project from Babcock Rd to Venado Trace.
    • JDA will be working on removal of driveways, curb, and sidewalk on the north side of the project from Babcock Rd to Venado Trace.

 

 

  • 5/16/2024 - 5/30/2024: 
    • Fox concrete will continue to work on curb wall, sidewalk on the south side of the project.
    • JDA will be working on road excavation on the north side of the project from Vendado Trace to Oakland Rd.
    • JDA will be working on removal of driveways, curb and sidewalk on the north side of the project from Venado Trace to Oakland Rd.  

 

 

 

  • 5/16/2024 - 5/30/2024: 
    • Fox concrete will continue to work on curb wall, sidewalk on the south side of the project.
    • JDA will be working on grading for sidewalk, curb wall and installation of railing on the south side of the project.  

 

 

  • 5/16/24 - 5/30/2024: Miller Bros will start working on the north side of the project starting at Network Blvd.  They will install fire hydrants, hydrostatic and chlorination test, 3 tie ins. 
  • 5/24/24 - 6/6/24:  Miller Bros will start working on the 12" WL from Sta 79+04 to 87+56. 

 

 


 

 

Project Update:  May 3, 2024

PLANNED UPCOMING ACTIVITIES:

  • 5/3/24 - 5/16/2024: JDA working on Verbena Rd. grading for paving operations.  Verbena Rd. between Oakland and Southwell Rd. to be closed to thru traffic.

 

  • 5/2/2024 - 5/16/2024:  AT&T will begin work at Jade Heights.

 

 

  • 5/1/2024 - 5/16/2024:  JDA will be working road excavation and removal of driveways, curbs, and sidewalks on the north side of the project from Babcock Rd. to Venado Trace. 
  • 5/2/2024 - 5/16/2024:  Fox concrete will continue to work on the curb wall, sidewalk on the south side of the project.
  • 5/2/2024 - 5/16/2024:  JDA will be working on grading for sidewalk, curb wall and installation of railing from Venado Trace to Oakland Rd.
  • 5/1/2024 - 5/8/2024:  Durham will be working on milling the asphalt on the north side of the project.
  • 5/1/2024 - 5/6/2024:  JDA will be working on grading for sidewalk, curb wall and installation of railing on the south side of the project.  

 

 

  • 5/2/2024 - 5/15/2024:  Miller Bros will start working on the north side of the project starting at Network Blvd.  They will install fire hydrants, 3 tie-ins, and an 8" waterline installation.  

 

NOTE TO BUSINESS OWNERS:

If your business is currently or expected to experience construction in your area please visit the City of San Antonio's Construction Toolkit. This guide helps business owners understand and prepare for City-initiated construction projects.

Business Outreach Specialist: 210-207-3922, [email protected]


Learn more about City projects in your neighborhood and across San Antonio. The City of San Antonio’s digital dashboards encompass a wide range of projects, including streets, drainage, parks, and facilities.


 

Question title

To receive project updates and details on future public meetings, please provide the following information.

Question title

Please share any feedback or questions about this project.

 

Excavation work continues on the north side of Prue Rd. looking West.

 

 

Excavation work and Box Culvert installs continue on the north side of Prue Rd. looking West.

 

 

Utility installation work on the north side of Prue Rd. looking East.