PROJECT UPDATE:

 
January 10, 2025
 

Prue Road is underway with Outfall C drainage boxes delivered, and the construction team is installing them at the time of this update. Curb and gutter installation is complete between Babcock and Woodwaters Way, and work continues on the shared use path and median concrete curb installation. Due to the low ambient temperature, paving operations will pause until the week of January 13, 2025. Please note that Lockhill Road will be closed to through traffic between Southwell and Oakland for installation of the Outfall C drainage boxes. You may detour via Prue Road or Hollyhock.


The closure is estimated for the next two weeks. 

Our current estimate for project completion is early 2025. 

 

PLANNED UPCOMING ACTIVITIES:

  • 01/08/25 - 01/15/25 
    • Fox Quality Concrete has completed the curb and gutter installation between Babcock and Woodwaters Way; gutter installation and work on shared use path continues in remaining locations
    • Median curb installation continues between Babcock and Woodwaters Way
  • 01/14/25 - 01/25/25: 
    • Final Surface paving between Babcock and Venado Trace will resume when temperatures reach COSA paving standards

  • 01/14/25 - 01/25/25: 
    • JDA placing final pavement layer between Woodwaters and Network
  • 01/08/25 - 01/20/25: 
    • Fox Quality Concrete working on shared use path, curb walls, driveways, curb ramps and median curbs between Woodwaters Way and Network
  • 01/14/25 - 01/28/25:
    • ​JDA working on bus pad installations and will continue with final paving from Network to Laureate
    • Fox Quality Concrete working on shared use path, curb walls, curb ramps, driveways and median curbs

  • 01/14/25: 
    • Outfall C drainage continues from just south of Lockhill then north towards Prue Road
  • ​01/09/25:
    • ​Lockhill closes to through traffic between Southwell and Oakland - for drainage construction box installation for Outfall C
    • Detour via Prue Road or Hollyhock starting 01/09/25 (approximately 2 weeks)
  • 01/06/25:
    • Outfall C drainage work continues between Verbena and Hollyhock

**PLEASE NOTE: ALL WORK IS SUBJECT TO FAVORABLE WEATHER CONDITIONS**


 

 

 

 
 
 
 
 

NOTE TO BUSINESS OWNERS:

If your business is currently or expected to experience construction in your area please visit the City of San Antonio's Construction Toolkit. This guide helps business owners understand and prepare for City-initiated construction projects.

Business Outreach Specialist: 210-207-3922, [email protected]


Learn more about City projects in your neighborhood and across San Antonio. The City of San Antonio’s digital dashboards encompass a wide range of projects, including streets, drainage, parks, and facilities.


 

Question title

To receive project updates and details on future public meetings, please provide the following information.

Question title

Please share any feedback or questions about this project.

 


Roller compacting asphalt behind paving machine near Venado Trace on North side of Prue Road

 

Excavation work, curb walls, curb ramps and bus pad installation vicinity Network to Laureate

 

 

Asphalt paving work on the north side of Prue Road looking East