Districts 1 and 9 Quiet Zone
Districts 1 and 9 Quiet Zone
The San Antonio Transportation Department will be making improvements to five Quiet Zone crossings within Districts 1 and 9 to maintain compliance with federal regulations.
Improvements include:
- Installing signs
- Adding and refreshing pavement markings
- Extension of raised concrete medians
For questions or comments regarding the Districts 1 and 9 Quiet Zone: call 855-925-2801 and enter code 10307. Or, email us at SAquietzones@publicinput.com.
What's Happening?
What's Happening?
Construction start: September 2026
Completion: December 2026*
Lane closures/Detours:
- W Sunset: Lane Closure – 3 days for signs/striping
- Jones Maltsberger: Lane Closure – 1 day for signs/striping
- Basse: Detour – 1 day for signs and striping and Lane Closure – 1 day for concrete work (2 days)
- Zilla: Detour – 1 day for signs and striping and 1 day for concrete work (2 days)
- Dora: Detour – 1 day for signs/striping
Total working days: 9 days
Crossings improvements will be staggered to help minimize any impact to travel. Please seek alternate routes during construction.
*Weather permitting