What's Happening?

Detours will be required for all crossings:

  • W Hollywood: Detour - 1 day for signs/striping
  • W Elsmere: Detour - 2 days for signs and striping and 1 day for concrete work (3 days)
  • W Kings Hwy: Detour - 1 day for signs/striping
  • W Summit: Detour - 1 day for signs/striping
  • W Magnolia: Detour - 1 days for signs and striping and 1 day for concrete work (2 days)
  • W Woodlawn: Detour - 1 day for signs/striping
  • W Russell: Detour - 1 day for signs/striping
  • W Ashby: Detour - 1 day for signs/striping
  • Hickman: Detour - 1 days for signs and striping and 1 day for concrete work (2 days)

Total working days: 14 days

 

 

Question title

Would you like to learn more? Sign up here for updates. Feel free to leave a comment, too!

Detours will be required for all crossings:  W Hollywood: Detour - 1 day for signs/striping W Elsmere: Detour - 2 days for signs and striping and 1 day for concrete work (3 days) W Kings Hwy: Detour - 1 day for signs/striping W Summit: Detour - 1 day for signs/striping W Magnolia: Detour - 1 days for signs and striping and 1 day for concrete work (2 days) W Woodlawn: Detour - 1 day for signs/striping W Russell: Detour - 1 day for signs/striping W Ashby: Detour - 1 day for signs/striping Hickman: Detour - 1 days for signs and striping and 1 day for concrete work (2 days) Total working days: 14 days