2022-2027 Bond Project: Classen Rd. (Classen Spur - Knollcreek Dr.)
2022-2027 Bond Project: Classen Rd. (Classen Spur - Knollcreek Dr.)
The project will construct roadway improvements to include sidewalks, curbs, driveway approaches, drainage, bicycle facilities, and other improvements as applicable and within available funding.
Project Type: Streets
Phase: Design Phase
Project Contact: Betsy Hove - (210) 207-7787
Estimated Construction Timeline: Winter 2026 - Summer 2027
Estimated Timeline Construction Seasons are identified as: Winter (January, February, March), Spring (April, May, June), Summer (July, August, September), and Fall (October, November, December).
Project Budget: | |
2022 General Obligation Bond (Streets) | $10,000,000.00 |
San Antonio Water System | $326,311.00 |
Total | $10,326,311.00 |
Project Limits:
NOTE TO BUSINESS OWNERS:
If your business is currently or expected to experience construction in your area please visit the City of San Antonio's Construction Toolkit. This guide helps business owners understand and prepare for City-initiated construction projects.