Churchill Ave. Area Drainage Improvements
Churchill Ave. Area Drainage Improvements
The Churchill Ave. Area Drainage Improvements Project constructed a drainage system comprised of culvert crossings and an earthen channel, improving low water crossings at Chole Drive, Churchill Avenue, and Minnie Street.
Phase: Construction
Project Budget: $2,960,000 (Storm Water Operating Fund)
Project Contact: Joe Hinojosa, (210) 207-2799
Estimated Construction Timeline: Spring 2024 - Fall 2024
Estimated Timeline Construction Seasons are identified as: Winter (January, February, March), Spring (April, May, June), Summer (July, August, September), and Fall (October, November, December.)
Project Limits:
Project Update 5/3/24:
- Contractor will be working on clearing channel area west of Chloe St and doing channel soil work east of Minnie St. Tree protection and fencing is also being installed.
NOTE TO BUSINESS OWNERS:
If your business is currently or expected to experience construction in your area please visit the City of San Antonio's Construction Toolkit. This guide helps business owners understand and prepare for City-initiated construction projects.
Business Outreach Specialist: 210-207-3922, [email protected]
Learn more about City projects in your neighborhood and across San Antonio. The City of San Antonio’s digital dashboards encompass a wide range of projects, including streets, drainage, parks, and facilities.