Project Update

October 17, 2024

 

 

Project at Substantial Completion:

 

We are excited to let you know that traffic is once again open in both the Northbound and Southbound lanes of Bulverde, as of the second week of October, 2024. The contractor will be working on a final punch list of repair items for the next 4 weeks. Please expect intermittent lane closures as they complete some of these final items of work. 

 

FINAL PROJECT COMPLETION ACTIVITIES:

 

  • Completed from September 25 - October 8, 2024:

    • Tree installation October 2, 2024
    • Final roadway striping layout September 25, 2024
    • Striping and paint completion date October 5, 2024
    • Final signal installs/programming complete on October 8, 2024
    • Both lanes open to traffic, as of the second week of October, 2024

 

 

 

 


SUPPORT YOUR LOCAL SMALL BUSINESSES: https://www.sanantonio.gov/EDD/Programs-Grants/Paving-The-Way

NOTE TO BUSINESS OWNERS:

If your business is currently or expected to experience construction in your area please visit the City of San Antonio's Construction Toolkit. This guide helps business owners understand and prepare for City-initiated construction projects.

Business Outreach Specialist: Gabby Tello, 210-207-4688


Learn more about City projects in your neighborhood and across San Antonio. The City of San Antonio’s digital dashboards encompass a wide range of projects, including streets, drainage, parks, and facilities.


 

Question title

* To receive project updates and details on future public meetings, please provide the following information.

Question title

Please share any feedback or questions about this project.