Wurzbach Corridor Sidewalk Project
Wurzbach Corridor Sidewalk Project
The Bond Project includes the construction of pedestrian mobility improvement projects as applicable and within available funding.
Project Type: Streets, Bridges, & Sidewalks
Phase: Construction Phase
Project Budget: $2.35 million
Project Contact: Betsy Hove, (210) 207-7787
Estimated Construction Timeline: July 2024 - Winter 2025
Estimated Timeline Construction Seasons are identified as: Winter (January, February, March), Spring (April, May, June), Summer (July, August, September), and Fall (October, November, December.)
Associated Projects:
Wurzbach at Vance Jackson Intersection Project
Project Limits: Wurzbach Road from Fredricksburg Road to IH-10
NOTE TO BUSINESS OWNERS:
If your business is currently or expected to experience construction in your area please visit the City of San Antonio's Construction Toolkit. This guide helps business owners understand and prepare for City-initiated construction projects.
Business Outreach Specialist: 210-207-3922, [email protected]
Learn more about City projects in your neighborhood and across San Antonio. The City of San Antonio’s digital dashboards encompass a wide range of projects, including streets, drainage, parks, and facilities.
Construction Updates:
Construction to Start - Wurzbach Corridor Sidewalks - Monday, July 29, 2024
Construction is scheduled to begin Monday, July 29, on a project to improve pedestrian amenities along Wurzbach Road from I-10 to Fredericksburg Road. Improvements include wider sidewalks, improved ADA accessibility, and better access to bus stops.
The $2.35 million project will be conducted in four phases, beginning with the area between I-10 and Bluemel Road. Work on the first three phases will be conducted primarily at night, seven days a week to minimize impacts to traffic.
The project is scheduled for completion in Winter 2025 (January-March). Two-way traffic will be maintained at all times. Businesses and their parking lots will remain accessible. There will be intermittent sidewalk closures.
- No parking on street 8 p.m. - 6 a.m.
- No parking at any time between Bluemel Rd. and Fernglen Rd.
- Vehicles in the path of the project will be towed to a nearby street.