2017-2022 Bond Project: Broadway Street Corridor (East Houston Street to East Hildebrand Avenue)
2017-2022 Bond Project: Broadway Street Corridor (East Houston Street to East Hildebrand Avenue)
The Lower Broadway Corridor Project includes improvements such as roadway reconstruction, curbs, sidewalks, driveway approaches, underground drainage, ADA wheelchair ramps, pedestrian lighting and amenities, landscaping, and utility upgrades. Substantial completion for this project will be Summer 2024.
Project Type: Streets, Bridges & Sidewalks
Phase: Complete
Project Contact: Joey Doctor, (210) 207-8415
Estimated Construction Timeline: Summer 2020 - Fall 2024
Estimated Timeline Construction Seasons are identified as: Winter (January, February, March), Spring (April, May, June), Summer (July, August, September), and Fall (October, November, December.)
Project Budget: |
| ||
2017 General Obligation Bond (Street) | $42,000,000.00 | ||
AT&T Contribution | $4,000,000.00 | ||
CPS Energy | $14,657,973.41 | ||
San Antonio River Authority | $396,195.37 | ||
San Antonio Water System | $8,226,091.53 | ||
Tax Increment Reinvestment Zone | $43,000,000.00 | ||
Tree Preservation Fund | $965,000.00 |
Total | $113,245,260.31 |
Construction Phasing (Roadway):
- Avenue B / N. Alamo Bike Lanes
- Roy Smith to Jones
- Brooklyn to Jones
- 3rd St. to Brooklyn
- Pecan St. to 3rd. St.
- E. Houston to Pecan St.
- Final Asphalt Overlay
Project Limits:
SUPPORT YOUR LOCAL SMALL BUSINESSES: https://www.sanantonio.gov/EDD/Programs-Grants/Paving-The-Way
NOTE TO BUSINESS OWNERS:
If your business is currently or expected to experience construction in your area please visit the City of San Antonio's Construction Toolkit. This guide helps business owners understand and prepare for City-initiated construction projects.
Business Outreach Specialist: Gabby Tello, 210-207-4688
Learn more about City projects in your neighborhood and across San Antonio. The City of San Antonio’s digital dashboards encompass a wide range of projects, including streets, drainage, parks, and facilities.
Construction Updates:
- Starting as early as the week of March 3, 2025, tree grate installation will begin. During installation of tree grates on Broadway, crews will setup rolling lane closures along the outside traffic lanes. Crews will be offloading grate frames, anchoring into concrete, then setting the iron grates. Rolling lane closures will only be on one side of the roadway at a time, stretching no more than two blocks in distance. Northbound and southbound traffic lanes will be opened at all times. Side streets will have full traffic access
- COSA punch list items are being worked on into March 2025
- Completed: Roadway, paving, sidewalks, landscaping, pedestrian lighting, bike racks, trash cans, traffic and pedestrian signals, and SAWS punch list items.
- The entire project corridor is open to vehicular traffic
- Avenue B, McCullough, and N. Alamo bike lanes are completed
- All work is weather permitting
Businesses remain open and accessible!
BUY LOCAL!
Project Presentation Documents