2022-2027 Bond Project: Marbach Road Area Streets & Drainage (Loop 410 to Horal Drive)
2022-2027 Bond Project: Marbach Road Area Streets & Drainage (Loop 410 to Horal Drive)
MARBACH AREA STREETS:
The Bond Project will construct roadway improvements to include sidewalks, curbs, driveway approaches, drainage and other improvements as applicable and within available funding.
Project Type: Streets, Bridges, & Sidewalks
Phase: Design
Project Contact: LaShondra Gladney, (210) 207-0620
Estimated Construction Timeline: Fall 2025 - Winter 2029
Estimated Construction Timeline Seasons are identified as: Winter (January, February, March), Spring (April, May, June), Summer (July, August, September), and Fall (October, November, December).
Project Budget: | |
2022 General Obligation Bond (Streets) | $15,000,000.00 |
CPS Energy | $1,521,960.00 |
San Antonio Water System | $2,811,080.00 |
Tree Preservation Fund | $700,000.00 |
Total | $20,033,040.00 |
MARBACH AREA DRAINAGE:
The Bond Project will upgrade an undersized existing storm drain system which may include associated road reconstruction, curbs, sidewalks, and driveway approaches as applicable and within available funding. This is a Hazard Mitigation Action Plan project.
Project Type: Drainage and Flood Control
Phase: Design
Project Contact: LaShondra Gladney, (210) 207-0620
Estimated Construction Timeline: Fall 2025 - Winter 2029
Estimated Construction Timeline Seasons are identified as: Winter (January, February, March), Spring (April, May, June), Summer (July, August, September), and Fall (October, November, December.)
Project Budget: | |
2022 General Obligation Bond (Drainage) | $15,800,000.00 |
Total | $15,800,000.00 |
Design Public Meeting: 2022-2027 Bond Project Marbach Road Area Streets & Drainage (Loop 410 to Horal Drive)
You are invited to the following Design Public Meeting:
Marbach Road Area Streets and Drainage (Loop 410 to Horal Drive)
Tuesday, December 10, 2024
6:00pm – 7:00pm
Living Faith Church
7801 Marbach Road
San Antonio, TX 78227
Join Public Works and Districts 4 & 6 to review the design for Marbach Road Area Streets and Drainage (Loop 410 to Horal Drive)
For more information, please contact:
LaShondra Gladney, Capital Projects Officer
210.207.0620
NOTE TO BUSINESS OWNERS:
If your business is currently or expected to experience construction in your area please visit the City of San Antonio's Construction Toolkit. This guide helps business owners understand and prepare for City-initiated construction projects.
Business Outreach Specialist: Jonathan Gasper, 210-207-6055
Learn more about City projects in your neighborhood and across San Antonio. The City of San Antonio’s digital dashboards encompass a wide range of projects, including streets, drainage, parks, and facilities.