South Gevers St. Drainage Improvements Phase 1
South Gevers St. Drainage Improvements Phase 1
This project will alleviate continuous drainage issues along S. Gevers and adjacent streets by installing an underground system along S. Gevers Street consisting of various pipe sizes and concrete boxes that will tie-in to an existing underground system on Nopal Street. The project will include the excavation of two drainage detention ponds, street reconstruction, curbs, sidewalks, driveways. New utilities, such as water, sewer and gas work, are also included.
Phase: Construction
For more information: Call Public Works Storm Water Division at 210-207-1332
Estimated Construction Timeline: Spring 2022-Summer 2024
Estimated Timeline Construction Seasons are identified as: Winter (January, February, March), Spring (April, May, June), Summer (July, August, September), and Fall (October, November, December.)
Project Limits:
NOTE TO BUSINESS OWNERS:
If your business is currently or expected to experience construction in your area please visit the City of San Antonio's Construction Toolkit. This guide helps business owners understand and prepare for City-initiated construction projects.
Business Outreach Specialist: Gabby Tello, 210-207-4688
Learn more about City projects in your neighborhood and across San Antonio. The City of San Antonio’s digital dashboards encompass a wide range of projects, including streets, drainage, parks, and facilities.
Project Update 2/6/24: South Gevers Street from Minnetonka Street to Cosgrove Street
South Gevers Street remains closed to through traffic.
Current and planned work:
- Southbound lanes on Gevers will be closed
- Northbound lanes on S. Gevers will be opened
- Driveway approaches will be opened during business hours
- Excavation on S. Gevers continues for future mill & overlay
- Installation of fire hydrant at Cosgrove St and S. Gevers
- Completion of inlet installation at Cosgrove St and S. Gevers intersection
Driveway into the Gevers Villa Shopping Center will remain open for access to Jewelry & Watch Repair Center, Unique Hair Styles, Farr Builders, LLC, and Trevino's Barbacoa.
Project Delays (5 months):
During project construction, a conflict was identified between the proposed storm drain system and a sewer line resulting in the redesign of both the storm drain system and the new sewer bypass system. Additionally, CPS Energy performed gas main and property service adjustments which caused bid item overruns and additional street reconstruction.